Which of the following is not an output of the project cost management process called estimating costs,

Question:

Which of the following is not an output of the project cost management process called estimating costs, according to the PMBOK® Guide – Sixth Edition?

a. Cost estimates

b. A cost baseline

c. Basis of estimates

d. Project documents updates