Which of the following statements is false? a. A burndown chart is a tool for schedule control.

Question:

Which of the following statements is false?

a. A burndown chart is a tool for schedule control.

b. Duration and effort are synonymous terms.

c. A three-point estimate includes an optimistic, a most likely, and a pessimistic estimate.

d. A Gantt chart is a common tool for displaying project schedule information.