Which of the following statements is false? a. A burndown chart is a tool for schedule control.
Question:
Which of the following statements is false?
a. A burndown chart is a tool for schedule control.
b. Duration and effort are synonymous terms.
c. A three-point estimate includes an optimistic, a most likely, and a pessimistic estimate.
d. A Gantt chart is a common tool for displaying project schedule information.