You are the project manager for a project that will develop in-house software used to monitor computer
Question:
You are the project manager for a project that will develop in-house software used to monitor computer parts inventory. Your project sponsor asks that you begin working on the WBS.
What is a WBS?
A. A breakdown of the project work activities B. A decomposition of the project scope C. Weekly deadlines for the project D. A topology of the project team’s responsibilities