You are the project manager for your organization. A change has been requested for your project. All

Question:

You are the project manager for your organization. A change has been requested for your project. All of the following are not valid responses to the proposed change request except for which one?

A. The proposed change cannot happen, but the project will require an extended timeline due to the time investigating the proposed change.

B. The proposed change can happen with the current resources but will require additional funding if the original deadline is to be met.

C. The proposed change can happen with the current resources and with the current financial obligations, but a change incorporation–processing fee must be applied.

D. The proposed change can be completed, but the timeline will need to be extended and an additional project manager will be required.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

It Project Management

ISBN: 9780071700436

3rd Edition

Authors: Joseph Phillips

Question Posted: