You are the project manager of the GHR Project for your organization. This project has just recently been initiated, and the requirements of the project have been agreed upon. Your sponsor would now like you to host a meeting that will review the agreement of the project objectives and establish the direction of the project. What type of a meeting does management want you to host?

A. Workshop B. Scope decomposition session C. Kickoff meeting D. Bidders conference