You had planned to construct a series of eight traffic roundabouts in your town, with each roundabout

Question:

You had planned to construct a series of eight traffic roundabouts in your town, with each roundabout costing

$150,000. Your goal was to complete the project during the four (4) months of good weather in the summer, but due to unexpected delays the project has not gone according to plan. After two months, earned value (EV) is calculated at $400,000. What is your budgeted cost at completion

(BAC)?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: