You work at a regional health care center and have been asked to calculate the expected cost
Question:
You work at a regional health care center and have been asked to calculate the expected cost for a software project in your organization. You know that historically your programmers can handle 5 function points each person-month and that the cost per programmer in your company is $4,000 per month. The project whose costs you are estimating is based on the following requirements:
a. Calculate the total estimated number of function points for this project.
b. Calculate the total expected cost of the project.