Your project is running out of budget allocation and significant work remains. You are directed by senior
Question:
Your project is running out of budget allocation and significant work remains. You are directed by senior management to instruct your team to charge their work time to another project’s account. Given these instructions you should A. Follow instructions B. Inform the corporate auditors C. Understand the background of management’s instructions before taking any action D. Shut down the project, if possible