Question: A project manager has a project team consisting of people in four countries. The project is very important to the company, and the project manager
A project manager has a project team consisting of people in four countries. The project is very important to the company, and the project manager is concerned about its success. The length of the project schedule is acceptable. What type of communication should he use?
A. Informal verbal communication B. * Formal written communication C. Formal verbal communication D. Informal written communication