According the PMBOK Guide, this system centrally manages approved changes and baselines within a project. A. Records

Question:

According the PMBOKĀ® Guide, this system centrally manages approved changes and baselines within a project.

A. Records management system B. Change control system C. Work authorization system D. Configuration management system