Question: Adams Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company
Adam’s Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam’s Construction is using:
A. analogous estimating.
B. * parametric estimating.
C. three-point estimating.
D. reserve analysis.