What are the performance measurements for the Control Schedule process? A. SV = (EV PV) and
Question:
What are the performance measurements for the Control Schedule process?
A. SV = (EV – PV) and SPI = (EV / PV)
B. SV = (EV – AC) and SPI = (EV / AC)
C. SV = (EV – BAC) and SPI = (EV / BAC)
D. SV = (PV – EV) and SPI = (PV / EV)