What are the performance measurements for the Control Schedule process? A. SV = (EV PV) and

Question:

What are the performance measurements for the Control Schedule process?

A. SV = (EV – PV) and SPI = (EV / PV)

B. SV = (EV – AC) and SPI = (EV / AC)

C. SV = (EV – BAC) and SPI = (EV / BAC)

D. SV = (PV – EV) and SPI = (PV / EV)