You accept project costs to date and assume future work (ETC) will be performed at the budgeted

Question:

You accept project costs to date and assume future work (ETC) will be performed at the budgeted rate. If BAC = 800, ETC = 275, PV = 300, AC = 200, EV = 250, and cumulative CPI = 1.25, what is the EAC?

A. 640 B. 750 C. 600 D. 550