You are a contract project manager for a wholesale flower distribution company. Your project is to develop

Question:

You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online.

You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower’s site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300, AC = 200, and EV = 250.

What do you know about this project?

A. The EAC is a positive number, which means the project will finish under budget.

B. You do not have enough information to calculate CPI.

C. The CV is a negative number in this case, which means you’ve spent less than you planned to spend as of the measurement date.

D. The CV is a positive number in this case, which means you’re under budget as of the measurement date.