You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. One of your users verbally requests changes to one of the screen displays. You explain to her that the change needs to go through the change control system, which is a subset of the configuration management system. You explain that a change control system does all of the following except for which one?

A. Documents procedures for change requests B. Tracks the status of change requests C. Describes the management impacts of change D. Determines whether changes are approved or denied