You are in the process of making project staff assignments. You have several candidates for a position
Question:
You are in the process of making project staff assignments. You have several candidates for a position on the project team that requires specific qualifications. All the candidates seem to meet the qualifications. You also consider prior experience, their interest in the project, cost rates, and availability of these potential candidates. Which of the following is true?
A. You are considering the resource calendars input of the Develop Project Team process.
B. You are considering the project staff assignments input of the Develop Project Team process.
C. You are considering the enterprise environmental factors input of the Acquire Project Team process.
D. You are considering the project management plan input of the Acquire Project Team process.
Step by Step Answer:
PMP Project Management Professional Exam Study Guide
ISBN: 9788126521890
5th Edition
Authors: Kim Heldman