You are performing actions such as analyzing past performance, assessing the current status of risks and issues,

Question:

You are performing actions such as analyzing past performance, assessing the current status of risks and issues, describing the work completed this period, and summarizing the changes approved this period. Which process are you performing?

A. Report Performance B. Integrated Change Control C. Monitor and Control Project Work D. Administer Procurements