You are performing the following activities: comparing actual performance against the project plan, assessing performance to determine
Question:
You are performing the following activities: comparing actual performance against the project plan, assessing performance to determine if a corrective action is necessary, identifying new risks, providing forecasts to update current cost and schedule data, and monitoring implementation of approved changes. Which process are you in?
A. Perform Integrated Change Control B. Report Performance C. Monitor and Control Project Work D. Monitor and Control Risks
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Project Management Professional Exam Study Guide
ISBN: 9788126521890
5th Edition
Authors: Kim Heldman