You are working on a project and discover that one of the business users responsible for testing the product never completed this activity. She has written an email requesting that one of your team members drop everything to assist her with a problem that could have been avoided if she would have performed the test. This employee reports to a stakeholder, not to the project team. You estimate that the project might not be completed on time as a result of this missed activity. All of the following are true except for which one?

A. You should recommend a corrective action to bring the expected future project performance back into line with the project management plan because of this employee’s failure to perform this activity.

B. You should recommend a preventive action to reduce the possibility of future project performance veering off track because of this employee’s failure to perform this activity.

C. You should recommend a change request, which is an output of the Monitor and Control Project Work process, to get the project performance back in alignment with the project management plan.

D. You might have to request a change to the project schedule as a result of this missed activity.