Question: You can use various estimating approaches to determine activity durations. When you have a limited amount of information available about your project, especially when in

You can use various estimating approaches to determine activity durations. When you have a limited amount of information available about your project, especially when in the early phases, the best approach to use is-

A. Bottom-up estimating B. * Analogous estimating C. Reserve analysis D. Parametric analysis