You know that BAC = 375, PV = 300, AC = 200, and cumulative EV = 250.
Question:
You know that BAC = 375, PV = 300, AC = 200, and cumulative EV = 250.
Variances that have occurred on the project to date are not expected to continue. What is the ETC?
A. 75 B. 50 C. 125 D. 150