You know that BAC = 500, PV = 325, AC = 275, CPI = .9, and EV
Question:
You know that BAC = 500, PV = 325, AC = 275, CPI = .9, and EV = 250, and you are using actual costs to date and assuming ETC uses the budgeted rate. Variance at completion tells you which of the following?
A. 25 B. –52 C. 52 D. –25