Your project was just completed. Because of some unfortunate circumstances, the project was delayed, causing cost overruns
Question:
Your project was just completed. Because of some unfortunate circumstances, the project was delayed, causing cost overruns at the end of the project. Which of the following statements is true?
A. You should document the circumstances as lessons learned.
B. You should pay particular attention to archiving the financial records for this project.
C. Your project ended because of starvation because of the cost overruns.
D. You should document the circumstances surrounding the project completion during the Scope Verification process.