Question: Youve consulted your earned value calculations to find out the EAC and ETC of your project. Which of the following is the BEST place to

You’ve consulted your earned value calculations to find out the EAC and ETC of your project. Which of the following is the BEST place to put that informations?

A. Work performance informations B. Quality control measurements C. * Forecasts D. Lessons learned