12. Slidell, Inc., employs two kinds of direct labor: assembly workers, who are paid $8 per hour, and skilled workers, who are paid $15 per hour. Slidell expects to produce 400 units next period, each of which will require 4 hours of assembly time and 3 hours of skilled labor.
Prepare a direct labor budget for next period.