6. Mackenzie Company uses a job costing system with four activity-based overhead pools: Cutting, allocated at $4.50

Question:

6. Mackenzie Company uses a job costing system with four activity-based overhead pools: Cutting, allocated at $4.50 per cut; Molding, allocated at $25 per machine hour; Assembly, allocated at 30% of direct labor cost; and Packing, allocated at $1,000 per order. A recent order from Rose, Inc., used $10,000 in direct materials, $12,000 in direct labor, 500 cuts, and 800 machine hours.

Calculate the cost of the Rose, Inc., order before accounting for spoilage and rework.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: