=+EX 23-8 Direct labor variances obj. 3 a. Rate variance, $730 U Alpine Bicycle Company manufactures
Question:
=+EX 23-8 Direct labor variances obj. 3
✔
a. Rate variance,
$730 U Alpine Bicycle Company manufactures mountain bikes. The following data for May of the current year are available:
Quantity of direct labor used 600 hrs.
Actual rate for direct labor $12.50 per hr.
Bicycles completed in May 280 Standard direct labor per bicycle 2 hrs.
Standard rate for direct labor $12.75 per hr.
Planned bicycles for May 310
a. Determine the direct labor rate and time variances.