=+PE 23-3A Factory overhead controllable variance obj. 4 EE 23-3 p. 1056 McLean Company produced 2,500 units
Question:
=+PE 23-3A Factory overhead controllable variance obj. 4 EE 23-3 p. 1056 McLean Company produced 2,500 units of product that required two standard hours per unit. The standard variable overhead cost per unit is $2.50 per hour. The actual variable factory overhead was $12,900. Determine the variable factory overhead controllable variance.