2. A project team is studying the downtime cost of a soft drink bottling line. Data analysis...
Question:
2. A project team is studying the downtime cost of a soft drink bottling line. Data analysis in thousands of dollars for a three-month period are: back-pressure regulator, 30; adjust feed worm, 15; jam copper head, 6; lost cooling, 52; valve replacement, 8; and other, 5.
Construct a Pareto diagram.