=11-13 Sid Davidson was able to determine the activity times for the leadership training program. He would

Question:

=11-13 Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and the critical path. The activity times appear in the following table (see Problem 11-12):

Activity Time (Days)

A 2 B 5 C 1 D 10 E 3 F 6 G 8 35