=11-15 The following are the activity times for the project in Problem 11-14. Find the earliest, latest,
Question:
=11-15 The following are the activity times for the project in Problem 11-14. Find the earliest, latest, and slack times for each activity. Then find the critical path.
Activity Time (Days)
A 3 B 7 C 4 D 2 E 5 F 6 G 3