=11-28 The estimated times (in weeks) and immediate predecessors for the activities in a project are given

Question:

=11-28 The estimated times (in weeks) and immediate predecessors for the activities in a project are given in the following table. Assume that the activity times are independent.

Activity Immediate Predecessors a m b A — 9 10 11 B — 4 10 16 C A 9 10 11 D B 5 8 11

(a) Calculate the expected time and variance for each activity.

(b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?

(c) What is the variance of the critical path? What is the variance of the other path in the network?

(d) If the time to complete path A–C is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

(e) If the time to complete path B–D is normally

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: