=11-29 The following costs have been estimated for the activities in a project: Activity Immediate Predecessors Time

Question:

=11-29 The following costs have been estimated for the activities in a project:

Activity Immediate Predecessors Time Cost ($)

A — 8 8,000 B — 4 12,000 C A 3 6,000 D B 5 15,000 E C, D 6 9,000 F C, D 5 10,000 G F 3 6,000

(a) Develop a cost schedule based on earliest start times.

(b) Develop a cost schedule based on latest start times.

(c) Suppose that it has been determined that the

$6,000 for activity G is not evenly spread over the three weeks. Instead, the cost for the first week is

$4,000, and the cost is $1,000 per week for each of the last two weeks. Modify the cost schedule based on earliest start times to reflect this situation.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: