=11-33 The Laurenster Corporation needs to perform the following tasks in weeks. Activity IMMEDIATE Predecessors Optimistic Time

Question:

=11-33 The Laurenster Corporation needs to perform the following tasks in weeks.

Activity IMMEDIATE Predecessors Optimistic Time Most Likely Time Pessimistic Time A 2 3 4 B 4 6 8 C 2 5 8 D A 3 4 5 E B 6 7 8 F C 4 7 10 G A 1 5 9 H B 2 5 8 I C 3 5 7 J D, G 2 2 2 K E, H 4 4 4 L F, I 3 3 3

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: