=11-33 The Laurenster Corporation needs to perform the following tasks in weeks. Activity IMMEDIATE Predecessors Optimistic Time
Question:
=11-33 The Laurenster Corporation needs to perform the following tasks in weeks.
Activity IMMEDIATE Predecessors Optimistic Time Most Likely Time Pessimistic Time A 2 3 4 B 4 6 8 C 2 5 8 D A 3 4 5 E B 6 7 8 F C 4 7 10 G A 1 5 9 H B 2 5 8 I C 3 5 7 J D, G 2 2 2 K E, H 4 4 4 L F, I 3 3 3