=11-35 There is a network of 25 activities and 13 nodes. The activity durations are normally distributed.

Question:

=11-35 There is a network of 25 activities and 13 nodes. The activity durations are normally distributed. The average duration MU and standard deviation, SIGMA are given in the Table, in weeks. The activities are already in topological order. Use the Project Management module in the QM package to obtain the project completion time. The fifth option in the module is for when the means and standard deviations of the activity durations are available.

ACTIVITY NO. K NODE S(K) NODE F(K) MU SIGMA 1 1 2 5.00 1.17 2 1 3 10.00 2.53 3 1 4 6.00 1.24 4 3 4 9.00 1.99 5 1 5 8.00 1.52 6 5 4 15.00 3.36 7 5 7 19.00 3.68 8 5 6 6.00 1.05 9 6 9 8.0 0.98 10 6 7 11.00 2.39 11 2 4 7.00 0.05 12 4 7 9.00 0.32 13 4 8 3.00 0.67 14 2 10 2.00 0.43 15 2 8 8.00 1.64 16 10 11 6.00 0.09 17 10 12 1.00 0.20 18 7 9 10.00 1.09 19 7 8 3.00 0.70 20 8 11 1.00 0.25 21 11 13 4.00 0.69 22 8 13 5.00 0.11 23 8 9 9.00 0.53 24 9 13 14.00 3.67 25 12 13 10.00 2.08

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: