=11-35 There is a network of 25 activities and 13 nodes. The activity durations are normally distributed.
Question:
=11-35 There is a network of 25 activities and 13 nodes. The activity durations are normally distributed. The average duration MU and standard deviation, SIGMA are given in the Table, in weeks. The activities are already in topological order. Use the Project Management module in the QM package to obtain the project completion time. The fifth option in the module is for when the means and standard deviations of the activity durations are available.
ACTIVITY NO. K NODE S(K) NODE F(K) MU SIGMA 1 1 2 5.00 1.17 2 1 3 10.00 2.53 3 1 4 6.00 1.24 4 3 4 9.00 1.99 5 1 5 8.00 1.52 6 5 4 15.00 3.36 7 5 7 19.00 3.68 8 5 6 6.00 1.05 9 6 9 8.0 0.98 10 6 7 11.00 2.39 11 2 4 7.00 0.05 12 4 7 9.00 0.32 13 4 8 3.00 0.67 14 2 10 2.00 0.43 15 2 8 8.00 1.64 16 10 11 6.00 0.09 17 10 12 1.00 0.20 18 7 9 10.00 1.09 19 7 8 3.00 0.70 20 8 11 1.00 0.25 21 11 13 4.00 0.69 22 8 13 5.00 0.11 23 8 9 9.00 0.53 24 9 13 14.00 3.67 25 12 13 10.00 2.08
Step by Step Answer:
Quantitative Analysis For Management
ISBN: 9789332578692
12th Edition
Authors: Barry Render, Ralph M. Stair, Michael E. Hanna