=4. Four cranes are being assigned to five construction jobs. One of the jobs will be delayed

Question:

=4. Four cranes are being assigned to five construction jobs. One of the jobs will be delayed until one of the cranes becomes available after finishing the first job.

An assignment model will be used. To allow specialized software to find a solution to this problem,

a. nothing special must be done to this problem.

b. one dummy crane must be used in the model.

c. one dummy job must be used in the model.

d. both a dummy job and a dummy crane must be used in the model.