During peak times, the entry gate at a large amusement park experiences an average arrival of 500 customers per minute, according to a Poisson distribution.
The average customer requires 4 seconds to be processed through the entry gate. The park’s goal is to keep the waiting time less than 5 seconds. How many entry gates are necessary to meet this goal?