Question
1. A pipeline constructed of carbon steel failed after 3 years operation. On examination it was found that the wall thickness had been reduced by
1. A pipeline constructed of carbon steel failed after 3 years operation. On examination it was found that the wall thickness had been reduced by corrosion to about half the original value. The pipeline was constructed of nominal 100 mm (4 in) schedule 40 pipe. inside diameter 102.3 mm (4.026 in). outside diameter 114.3 mm (4.5 in). Estimate the rate of corrosion in ipy and mm per year.
2. The pipeline was used to carry wastewater to a hold-up tank. The effluent is not hazardous. A decision has to be made on what material to use to replace the pipe. Three suggestions have been made:
a. Replace with the same schedule carbon steel pipe and accept renewal at 3-year intervals.
b. Replace with a thicker pipe, schedule 80, outside diameter 114.3 mm (4.5 in), inside diameter 97.2 mm (3.826 in).
c. Use stainless steel pipe, which will not corrode.
The estimated cost of the pipes per unit length is: schedule 40 carbon steel $5, schedule 80 carbon steel $8.30, stainless steel (304) schedule 40 $24.80.
Installation and fittings for all the materials adds $16.5 per unit length. The downtime required to replace the pipe does not result in a loss of production. If the expected future life of the plant is 7 years, recommend which pipe to use.Step by Step Solution
3.36 Rating (159 Votes )
There are 3 Steps involved in it
Step: 1
1 Inside diameter d i 4026 in Outside diameter d 0 45 in Initial thickness t 0 d 0 d i 2 0237 inch F...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
6096324d3d342_26696.pdf
180 KBs PDF File
6096324d3d342_26696.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started