Question

1 Approved Answer

1. In a resource-constrained project the second priority in assigning resources is usually given to activities with the a) Smallest duration b) Least slack c)

1. In a resource-constrained project the second priority in assigning resources is usually given to activities with the

a) Smallest duration

b) Least slack

c) Most slack

d) Lowest identification number

e) Highest cost

2. All of the following are kinds of resource constraints except

a) Materials

b) People

c) Equipment

d) Information

e) All of the above are resource constraints

3. Project budgets are developed by time-phasing which of the following?

a) Resource schedules

b) Work packages

c) The network diagram

d) Both A and C are correct

e) A, B, and C are all correct

4. The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk

a) Assessment form

b) Responsibility matrix

c) Scenario assessment

d) Impact assessment

e) Risk severity matrix

5. The demolition of the Seattle Kingdome (Snapshot from Practice) is an example of which of the following?

a) Mitigating

b) Retaining

c) Ignoring

d) Transferring

e) Sharing

Step by Step Solution

3.46 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

1 a Smallest durati... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Thermodynamics for Engineers

Authors: Kenneth A. Kroos, Merle C. Potter

1st edition

1133112862, 978-113311286

More Books

Students also viewed these General Management questions