Question
A company has received a contract for producing 20.000 units of a certain product, delivered in weekly quantities of the same order. This delivery should
A company has received a contract for producing 20.000 units of a certain product, delivered in weekly quantities of the same order. This delivery should be spread over six months. The company works 250 days per year and the machines run 40 hours a week (5 x 8 h).
The next table describes the tasks, their immediate predecessors and the time needed for each task.
Task | Time needed (in seconds) | Immediate predecessors |
A | 150 | None |
B | 120 | A |
C | 150 | B |
D | 30 | A |
E | 100 | D |
F | 40 | C,E |
G | 30 | E |
H | 100 | F,G |
Making use of the principle of dynamic programming, design a production line, compute the cycle time and also give the efficiency of this production line.
The customer asks to push up the production with 10%. How do you react? What is your opinion? Be complete in your answer.
Step by Step Solution
3.36 Rating (149 Votes )
There are 3 Steps involved in it
Step: 1
The contract requires delivery of 20000 units over ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started