Question

1 Approved Answer

A company has received a contract for producing 20.000 units of a certain product, delivered in weekly quantities of the same order. This delivery should

A company has received a contract for producing 20.000 units of a certain product, delivered in weekly quantities of the same order. This delivery should be spread over six months. The company works 250 days per year and the machines run 40 hours a week (5 x 8 h).

The next table describes the tasks, their immediate predecessors and the time needed for each task.


Task

Time needed (in seconds)

Immediate predecessors

A

150

None

B

120

A

C

150

B

D

30

A

E

100

D

F

40

C,E

G

30

E

H

100

F,G

Making use of the principle of dynamic programming, design a production line, compute the cycle time and also give the efficiency of this production line.

The customer asks to push up the production with 10%. How do you react? What is your opinion? Be complete in your answer.

Step by Step Solution

3.36 Rating (149 Votes )

There are 3 Steps involved in it

Step: 1

The contract requires delivery of 20000 units over ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these Accounting questions

Question

What is your opinion of pharmaceutical advertising?

Answered: 1 week ago