Question

1 Approved Answer

A construction company has taken up a project to build a high-rise office complex. The time required to complete a construction project is normally distributed

A construction company has taken up a project to build a high-rise office complex. The time required to complete a construction project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. A construction company must pay a penalty if the project is not finished by the due date in the contract.

(a) If a construction company bidding on this con- tract puts in a due date of 80 weeks, what is the probability that they will have to pay a penalty?

(b) If a construction company bidding on this con- tract wishes to be 90% sure of finishing by the due date, what due date (project week #) should be negotiated?

Step by Step Solution

3.40 Rating (153 Votes )

There are 3 Steps involved in it

Step: 1

X Time required to complete a construction project x N 80 R 100 a Given that a construction com... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics A Decision Making Approach

Authors: David F. Groebner, Patrick W. Shannon, Phillip C. Fry

9th Edition

013302184X, 978-0133021844

More Books

Students also viewed these Mathematics questions

Question

Using (1) or (2), find L(f) if f(t) if equals: t cos 4t

Answered: 1 week ago