Question
An assembly line requires two components: Gadjits and widgets. Gadjits are produced by center 1 and widjets produced by center 2. Each unit of the
An assembly line requires two components: Gadjits and widgets. Gadjits are produced by center 1 and widjets produced by center 2. Each unit of the end item, called a jit-together, requires 3 gadjits and 2 widjets. The daily production quota of the assembly line is 775 jittogethers. The container for gadjits holds 70 units. The policy variable for center 1 is set at 0.07. The average waiting time for a container of gadjits is 0.08 day, and 0.07 day is needed to produce a container. The container for widgets holds 40 units and the policy variable for center 2 is 0.06. The average waiting time per container of widgets is 0.16 day, and the time required to process a container is 0.16 day. How many containers are needed for gadjits?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
The end item Jit requires 3 gadjits which are produced at centre I and 2 widgets which are produced ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
6094315b94c54_24585.pdf
180 KBs PDF File
6094315b94c54_24585.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started