An order for 100 of a product is processed on work centers A and B. The setup time on A is 50 minutes, and run
An order for 100 of a product is processed on work centers A and B. The setup time on A is 50 minutes, and run time is 5 minutes per piece. The setup time on B is 60 minutes, and the run time is 5 minutes per piece. Wait time between the two operations is 5 hours. The move time between A and B is 40 minutes. Wait time after operation B is 5 hours, and the move time into stores is 3 hours. Queue at work center A is 25 hours and at B is 35 hours.
Required:
Calculate the total manufacturing lead time for the order.
Step by Step Solution
3.55 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
Calculate manufacturing lead time Manufacturing lead time includes queue time setup time run ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
609745e09c2e8_27681.pdf
180 KBs PDF File
609745e09c2e8_27681.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started