An order for 100 of a product is processed on work centers A and B. The setup time on A is 50 minutes, and run

An order for 100 of a product is processed on work centers A and B. The setup time on A is 50 minutes, and run time is 5 minutes per piece. The setup time on B is 60 minutes, and the run time is 5 minutes per piece. Wait time between the two operations is 5 hours. The move time between A and B is 40 minutes. Wait time after operation B is 5 hours, and the move time into stores is 3 hours. Queue at work center A is 25 hours and at B is 35 hours.


Required:

Calculate the total manufacturing lead time for the order.

Step by Step Solution

3.55 Rating (148 Votes )

There are 3 Steps involved in it

Step: 1

Calculate manufacturing lead time Manufacturing lead time includes queue time setup time run ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
609745e09c2e8_27681.pdf

180 KBs PDF File

Word file Icon
609745e09c2e8_27681.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Materials Management

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

8th edition

9386873249, 134156323, 978-9386873248

More Books

Students also viewed these Accounting questions

Question

9-34. Define Benfords Law.

Answered: 1 week ago