Question

1 Approved Answer

During 2014, AM Construction Company changed from the completed-contract method to the percentage-of-completion method for accounting purposes but not for tax purposes. Gross profit figures

During 2014, AM Construction Company changed from the completed-contract method to the percentage-of-completion method for accounting purposes but not for tax purposes. Gross profit figures under both methods for the past three years appear below:

Completed-Contract Percentage-of-Completion

2012 $ 400,000 $ 800,000

2013 600,000 900,000

2014 700,000 1,000,000

$1,700,000 $2,700,000

Assume an income tax rate of 35% for all years.

Show computations to determine the adjustment needed in 2014 to the beginning balance of retained earnings to account for the effect of this accounting change on prior periods.

Step by Step Solution

3.48 Rating (158 Votes )

There are 3 Steps involved in it

Step: 1

Construction in ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting principles and analysis

Authors: Terry d. Warfield, jerry j. weygandt, Donald e. kieso

2nd Edition

471737933, 978-0471737933

More Books

Students also viewed these Accounting questions

Question

5 Identify the functions performed by wholesaling intermediaries.

Answered: 1 week ago