Eve, the owner of Eva?s Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:
Eve, the owner of Eva?s Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:
If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?
Job *** < Y N Processing Time (hrs) 3 1 4 2 5 Due (hrs from now) 5 1 9 3 37
Step by Step Solution
★★★★★
3.49 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
Job sequence as per SPT ...