Hi-Ho Yo-Yo, Inc. It was a little past 9:00 on a Monday morning when Jeff Baker walked into your office with a box of donuts.
Hi-Ho Yo-Yo, Inc. It was a little past 9:00 on a Monday morning when Jeff Baker walked into your office with a box of donuts.
"I've been talking with Anne about a problem we have with shortterm capacity in our pad printing operation. You know, that's where Imprint the logo on the Custom lines of yo-yos. We have received more orders than usual for July, and I want to release the orders to pad printing in a way that will enable us to meet our due date commitments in the best way possible. Would you have time to look at the order list (attached) and see what kind of schedule we should allow to do that? By the way, you have established quite a reputation in your short stay here. You have a talent for really explaining why your recommendations are the best approach in a way that all of us over-the-hill managers can understand. Please be sure to do that for me too. I want to understand why your recommendation is the best schedule and what the tradeoffs are for other possible schedules-- and none of that philosophical college mumbo-jumbo. Remember, I came up through the ranks. I don't have one of those sheepskins on my wall," he says with a laugh.
Since your schedule was back to normal after that MRP report you did for Anne, you agreed to look at the information. After that compliment, how could you say no? "Try to get back to me within a couple of days," Jeff said as he left your office.
After a few minutes with your old operations management text, you call the production control office to confirm the pad printing schedule. They confirm that pad printing runs one eight-hour shift per day. They tell you that due to a make-up day for flooding in June, pad printing will be running 23 days in July, beginning Friday, July 1 (they will work three Saturdays on July 9, 16, and 23, and take a one-day holiday for July 4). You thank them for the information and then you begin to develop your plan.
Even though Jeff lacks a college degree, from what you have seen, he is very sharp. And obviously he knows good work when he sees it since he liked, and apparently understood, your past work. You resolve to cover all the bases but in a way that is as clear as possible. PAD
PRINTING ORDER LIST
(See attachment for a proper graph)
JOB --- Date Order Received -----Set-up Time------ Production Time----- DUE DATE
A ----------------6/4------------------------- 2hrs. -----------------6 days-------------- 11 July
B --------------6/7 ----------------4hrs. --------------------------2 days -----------------8 July
C --------------6/12----------------- 2hrs.-------------------------- 8 days ---------------25 July
D -----------------6/14----------------- 4hrs. ----------------------3 days ----------------19 July
E ----------------6/15 -----------------4 hrs.--------------------- 9 days------------------ 29 July
Note: Setup time is to set up the pad printer at the start of the job. Setup includes thoroughly cleaning the printing heads and ink reservoirs, installing the new pad(s) and ink supply, and carefully aligning the machine. Setup at the beginning of a new day with the same job is insignificant.
Ignore DD priority rule given in the case instead use EDD rule.
1. Apply FCFS, SPT (also referred as SOT), EDD and CR priority rules and summarize your findings of each.
2. If you are in the position of decision maker, which rule will you recommend? Why?
3. What are the benefits of this rule?
4. What are the drawbacks of other rules?
5. How did you tackle setup time given in the case study?
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
Step: 1
From the above scenario we have received all the required information and data We a...See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started