Material Cost Per Yard Standard = $2.00 Actual = $2.10 Standard Yards per Unit = 4.5 yards and 4.75 yards Units of Production = 9,500
Material Cost Per Yard
Standard = $2.00
Actual = $2.10
Standard Yards per Unit = 4.5 yards and 4.75 yards
Units of Production = 9,500
1. Calculate the Total Direct Materials cost variance using the above information:
a. $9,262.50 Unfavorable
b. $9,262.50 Favorable
c. $3,780.00 Unfavorable
d. $3,562.50 Favorable
2. Calculate the Direct Materials Price variance using the above information:
a. $1,795.50 Favorable
b. $378.00 Favorable
c. $4,512.50 Unfavorable
d. $378.00 Unfavorable
3. Calculate the Direct Materials Quantity variance using the above information:
a. $4,512.50 Unfavorable
b. $4,512.50 Favorable
c. $4,750 Unfavorable
d. $4,750 Favorable
Step by Step Solution
3.37 Rating (153 Votes )
There are 3 Steps involved in it
Step: 1
Standard Actual Material Cost Per Yard 200 210 Standard Yards per Uni... View full answer

Get step-by-step solutions from verified subject matter experts
100% Satisfaction Guaranteed-or Get a Refund!
Step: 2Unlock detailed examples and clear explanations to master concepts

Step: 3Unlock to practice, ask and learn with real-world examples

See step-by-step solutions with expert insights and AI powered tools for academic success
-
Access 30 Million+ textbook solutions.
-
Ask unlimited questions from AI Tutors.
-
Order free textbooks.
-
100% Satisfaction Guaranteed-or Get a Refund!
Claim Your Hoodie Now!

Study Smart with AI Flashcards
Access a vast library of flashcards, create your own, and experience a game-changing transformation in how you learn and retain knowledge
Explore Flashcards