Question
Steel Signs Limited produces roadside signs using two separate processes. The company has recently employed a new CFO, Bob Chen, who previously worked in the
Steel Signs Limited produces roadside signs using two separate processes. The company has recently employed a new CFO, Bob Chen, who previously worked in the service industry and is unfamiliar with some of the issues arising in manufacturing operations. In particular, Mr Chen is concerned about the level of spoilage and wants advice on how this could be better managed. The company’s production processes are split into two separate departments. The Fabrication Department produces the blank signs (“the units”), where steel sheeting is cut into the required shapes and steel posts are welded to the signs. These blank units are then transferred to the Finishing Department, which prints the required signage onto the units and then fires them to set the paint finish.
The production process in the Fabrication Department is illustrated below. Conversion costs are added evenly through-out the production process:
Addition of steel (0%) --- Addition of steel posts (80%) --- Inspection (85%) --- Completion (100%) --- Transfer out of unit (At end)
The production process in the Finishing Department is illustrated below. Conversion costs are also added evenly through-out this production process:
Transfer in of units (At start) --- Addition of paint (30%) --- Inspection (90%) --- Packaging of units (95%) --- Completion (100%)
At the start of September 2018 the Fabrication Department had 275 partially finished units that were 90% complete. During the month 2,200 units were completed and transferred to the Finishing Department and the ending work-in-progress was 250 units, 75% complete. The total spoilage for the month was 210 units, and normal spoilage is 2% of the good units passing inspection in the current month, on average.
The costs for the Fabrication department are collated below:
Costs | Fabrication Department |
Opening work-in process: | |
Steel | $6,180 |
Steel posts | $4,125 |
Direct Labour | $1,000 |
Overheads | $1,200 |
Costs added during October: | |
Steel | $60,000 |
Steel posts | $25,000 |
Direct Labour | $8,300 |
Overheads | $10,200 |
The Finishing Department had 260 units 25% complete at the start of the period. During the month 2,300 good units were completed and transferred to finished goods, and closing work-inprogress was 30 units, 50% complete. Normal spoilage is 5% of the good units passing inspection in the current month, on average
A summary of the costs in the Finishing Department has been provided below:
Costs | Finishing Department |
Opening work-in process | |
Transferred-in costs | $11,500 |
Direct Labour | $600 |
Overhead Costs | $600 |
Costs added during October: | |
Transferred-in Costs | ??? |
Paint | $12,500 |
Packaging | $5,000 |
Direct Labour | $25,000 |
Overhead Costs | $27,000 |
Required:
Taking the role of the management accountant for the company:
Your CFO, Bob Chen, doesn’t understand why spoilage is included in the process costing report and, in particular, asks you “why don’t we just eliminate the spoilage?” and “what do we do with all these spoiled units?”.
Prepare a memo for Mr Chen that explains how normal and abnormal spoilage is treated in process costing. Discuss why spoilage arises in the production process and why the targeted normal spoilage is not, usually, 0%. Include in your discussion, a consideration of how the normal spoilage percentage is determined and what procedures need to be put in place to monitor the levels of spoilage. Highlight for the CFO when corrective action should be taken in managing spoilage. Finally, discuss what happens to the spoiled units once they have been identified and how this does or does not affect the process cost report.
Step by Step Solution
3.19 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
Explaining to CEO Normal spoilage needs to be allocated when cost accounting Specifically you need t...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
60956fbbc4ee4_25867.pdf
180 KBs PDF File
60956fbbc4ee4_25867.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started