Question

1 Approved Answer

The acme Manufacturing company in Los Angeles is faced with a capacity issue in its assembly section. The demand calls for 40 units a week.

The acme Manufacturing company in Los Angeles is faced with a capacity issue in its assembly section. The demand calls for 40 units a week. However, the assembly cell is not keeping up to that rate of demand. There are 6 skilled workers, and the average time for a worker to produce a unit is 8 hours. The factory works 40 hours a week.

The management can either add another skilled worker (to bring the total to 7 workers) or can bring in a piece of machinery that can pre-assemble the sub-assembly and increase the production rate to 6 hours per unit. Which option would you select and why? (Show your computation)

a. Equipment to pre-assemble sub-assembly

b. Additional skilled worker.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

a Equipment to preassemble subassembly After this machine is installed ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
608ef6cd28530_20745.pdf

180 KBs PDF File

Word file Icon
608ef6cd28530_20745.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistics For Engineers And Scientists

Authors: William Navidi

3rd Edition

73376345, 978-0077417581, 77417585, 73376337, 978-0073376332

More Books

Students also viewed these General Management questions

Question

Who are serial entrepreneurs?

Answered: 1 week ago