The manager of a large group of employees must decide if she needs another copying machine. The cost of a machine is $275 per 8-hour
The manager of a large group of employees must decide if she needs another copying machine. The cost of a machine is $275 per 8-hour day whether or not the machine is in use. An average of 16.5 people per hour need to use the copying machine. Each person uses the copier for an average of 3.5 minutes. The employee cost is $31 per hour, and we assume that a waiting cost is incurred when a worker is waiting in line.
How many copying machines should be rented to minimize cost?
Step by Step Solution
★★★★★
3.62 Rating (149 Votes )
There are 3 Steps involved in it
Step: 1
Calculate rent of one copying machine costs and employees cost Average number of persons that need t...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
60947818f015c_24881.pdf
180 KBs PDF File
60947818f015c_24881.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started